Are you pressed for time and haven’t started working on your assignment yet? Would you like to buy an assignment? Use our custom writing services for better grades. Even if your deadline is approaching fast, our writers can handle your task right when you need it. Our writers will complete your order from scratch and make sure it’s completely unique.
Order a Similar Paper Order a Different Paper
QUESTION 1
- After your team has successfully identified potential risks that could affect the project, what is the next step?
Mitigate risks |
||
Assess identified risks |
||
Decide how to respond to all risks |
||
Create a risk breakdown structure |
||
Create contingency plans |
2.5 points
QUESTION 2
- This response is used to increase the potential effect of an identified Opportunity.
Exploit |
||
Share |
||
Accept |
||
Enhance |
2.5 points
QUESTION 3
- A Risk Response Matrix contains all of the following EXCEPT
Trigger. |
||
Who is responsible. |
||
Response. |
||
Contingency plan. |
||
When the risk will occur. |
2.5 points
QUESTION 4
- The implications of an identified change need to be assessed by:
The Chief Fiscal Officer. |
||
A person with expertise related to the change. |
||
The authorizing project manager. |
||
The primary project stakeholder. |
2.5 points
QUESTION 5
- Which of the following is NOT involved in risk control?
Establishing contingency funds |
||
Initiating contingency plans |
||
Establishing a change control system |
||
Watching for new risks |
||
Executing the risk response strategy |
2.5 points
QUESTION 6
- The initial step in the risk management process is to
Set aside budget funds for managing the risks. |
||
Determine the level of acceptable risk. |
||
Identify the risks. |
||
Assess the risk potential. |
||
Appoint a risk manager. |
2.5 points
QUESTION 7
- An uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives is termed a
Disaster. |
||
Random chance. |
||
Risk. |
||
Hazard. |
||
Bad luck. |
2.5 points
QUESTION 8
- Adopting proven technology instead of experimental technology in order to eliminate technical failure would be an example of which risk response?
Retaining |
||
Avoiding |
||
Transferring |
||
Ignoring |
||
Mitigating |
2.5 points
QUESTION 9
- Organizations use ________ in conjunction with work breakdown structures to help management teams identify and eventually analyze risk.
Contingency breakdown structures |
||
Risk breakdown structures |
||
Organizational breakdown structure |
||
Risk assessment |
||
Scenario analysis |
2.5 points
QUESTION 10
- This response is used when an identified Opportunity is not actively pursued.
Share |
||
Accept |
||
Exploit |
||
Enhance |
2.5 points
QUESTION 11
- Regina’s boss has told her that her project is very important. If the critical path is delayed, she will be given whatever she needs to get it back on schedule. Her project is classified as ________ constrained.
Cost |
||
Time |
||
Performance |
||
Quality |
||
Resource |
2.5 points
QUESTION 12
- Resource leveling or smoothing can have all the following results on a project EXCEPT
A longer project duration. |
||
Lower peak resource demand. |
||
Reduced fluctuations in resource demand. |
||
A more sensitive network. |
||
Reduced resource need over the life of the project. |
2.5 points
QUESTION 13
- Which of the following is NOT one of the more common problems associated with scheduling multiproject resources?
Delays in one project causing delays in other projects |
||
Overall schedule slippage |
||
Decline in project quality |
||
Resource bottlenecks |
||
Inefficient resource utilization |
2.5 points
QUESTION 14
- Splitting an activity can result in all of the following EXCEPT
A resource being moved from one activity to another and then back. |
||
Possible startup and shutdown costs. |
||
A better project schedule. |
||
Activity work being placed on hold for a period until more resources are available. |
||
More people working on the same activity. |
2.5 points
QUESTION 15
- In a resource-constrained project the second priority in assigning resources is usually given to activities with the
Most slack. |
||
Least slack. |
||
Highest cost. |
||
Lowest identification number. |
||
Smallest duration. |
2.5 points
QUESTION 16
- In a resource-constrained project, which of the following is most likely to be changed?
The budget |
||
The completion date |
||
Scope creep |
||
Project quality |
||
Resource levels |
2.5 points
QUESTION 17
- Rachel is working on a project that technically allows three activities to be done at the same time. If they were to be implemented at the same time, she would need 5 contractors in order for the activities to be completed on time. There are only 3 available for her to use. This is an example of what type of constraint?
Equipment |
||
Materials |
||
Physical |
||
People |
||
Technical |
2.5 points
QUESTION 18
- When deciding which staff to team-up to work on work packages, factors to consider are:
Years of working in the company. |
||
Practical Experience. |
||
Work habits. |
||
All of these choices are correct. |
2.5 points
QUESTION 19
- All of the following are types of resource constraints EXCEPT
Information. |
||
People. |
||
Materials. |
||
Human. |
||
Equipment. |
2.5 points
QUESTION 20
- All of the following are benefits of scheduling resources before project implementation EXCEPT
Work packages can be time-phased. |
||
The project completion date can be established. |
||
It allows managers to share resources with other project managers if it is requested without negatively impacting their project. |
||
It allows time for considering reasonable options if resource constraints do exist. |
||
It ensures low network sensitivity. |
2.5 points
QUESTION 21
- All of the following are disadvantages of scheduling overtime EXCEPT
Sustained overtime work by salaried employees may incur burnout. |
||
Productivity is reduced the longer one is working. |
||
More hours results in higher expenses if paying workers hourly. |
||
Continued overtime can lead to a higher turnover rate. |
||
Overtime is associated with additional costs of coordination and communication. |
2.5 points
QUESTION 22
- Emily has recently learned that she needs to reduce the duration of her project to meet an imposed deadline. She has calculated the crash cost per unit and knows the maximum units each activity can be reduced. What is the next step?
Find the activity with the highest crash cost |
||
Calculate the crash point |
||
Calculate the optimum cost-time point |
||
Find the activity with the lowest crash cost |
||
Identify the critical path |
2.5 points
QUESTION 23
- A contractor finished a bridge across a lake 18 months early and received more than $6 million for the early completion. This is an example of reducing project duration caused by
Incentive contracts. |
||
High overhead. |
||
Imposed project deadlines. |
||
Unforeseen project delays. |
||
Time to market. |
2.5 points
QUESTION 24
- Which of the following is NOT a technique for accelerating project completion when resources are not constrained?
Do it twice-first fast and then correctly |
||
Compromise quality |
||
Reduce project scope |
||
Assign additional staff and equipment |
||
Establish a core team |
2.5 points
QUESTION 25
- When reducing project duration, the duration for a project that is optimal is at the point where
Direct costs equal indirect costs. |
||
Indirect costs are the lowest. |
||
Direct costs are the lowest. |
||
Total project costs are the lowest. |
||
The project changes from time-constrained to resource-constrained. |
2.5 points
QUESTION 26
- According to Brooks’ Law, adding more people to a late project is most likely to have which of the following impacts?
Make the project slip further |
||
Decrease team motivation |
||
Keep the project from slipping any further |
||
Lead to burnout |
||
Get the project back on schedule |
2.5 points
QUESTION 27
- As a project is crashed and project duration is reduced, direct costs typically
Decrease. |
||
Become unreliable. |
||
Increase. |
||
Become unstable. |
||
Stay the same. |
2.5 points
QUESTION 28
- In selecting the best activity to crash you would first select the activity with the
Least steep slope. |
||
Largest crash time. |
||
Earliest start time. |
||
Longest duration. |
||
Most steep slope. |
2.5 points
QUESTION 29
- The direct cost for completing an activity in the shortest time it can realistically be completed in is called its ________ cost.
Accelerated |
||
Reserve |
||
Expedited |
||
Crash |
||
Normal |
2.5 points
QUESTION 30
- As a project is crashed and project duration is reduced, indirect costs typically
Decrease. |
||
Stay the same. |
||
Increase. |
||
Become unstable. |
||
Become unreliable. |
Do you need help with this or a different assignment? Even when your task is complicated and the deadline is in less than 2 days, you still have every chance to get a good grade for it. How? By completing the order form, you will get the finest custom-written assignment at an affordable price. We also deliver a number of services for free (e.g., revisions, editing, checking the text for authenticity). Use our paper writing service to receive effective help with your homework.
Order a Similar Paper
Order a Different Paper
Do you need help with this or a different assignment? Even when your task is complicated and the deadline is in less than 2 days, you still have every chance to get a good grade for it. How? By completing the order form, you will get the finest custom-written assignment at an affordable price. We also deliver a number of services for free (e.g., revisions, editing, checking the text for authenticity). Use our paper writing service to receive effective help with your homework.
Order a Similar Paper Order a Different Paper